Infrastructure Construction in Progress
Infrastructure Improvements in Huntington Beach
Construction in Progress
Updated September 2012
Questions call (714) 536-5430
Roadway Rehabilitation Project - CC-1397
Project Location: Main Street between Utica Street and Adams Avenue and on Garfield between Delaware and Beach Boulevard
Project Need: Replace warn-out roadway surface with new asphaltic concrete on designated streets.
Project Scope: Remove some of the parkway trees, replace portions of the sidewalk, install ADA ramps and grind and pave the roadway.
Schedule: Construction will begin in September, 2012 with a forecasted completion in early Jan 2013.
Traffic Control / Street Closures: Up to one lane closed in each direction of travel for up to a period of 10 days per occasion with parking restrictions. Occasional late evening, early morning and weekend work.
Cost: $1.2 million
Funding Sources: Gas Tax Funds and CalRecycle Grant Funds
Safe routes to School Project - CC-1402
Project Location:In the Vicinity of Golden View Elementary School
Project Need: Provide for safe passage for children going to and from school.
Project Scope: Install ADA ramps and grind. Modify the traffic signal at the intersection of Golden West Street and Slater Avenue
Schedule: Construction will begin in September, 2012 with a forecasted completion in early Jan 2013.
Traffic Control / Street Closures: Limited “No Parking” areas within residential streets and Lane closures for the traffic signal work.
Cost: $141,141 dollars
Funding Source:State SR2S Grant & Gas Tax Funds
Algonquin Sewer Lift Station and Force Main Replacement Project - CC-1415
Project Location: On Algonquin between Pearce and BoardwalkÂ
Project Need: Replace antiquated sewer lift station and force main.
Project Scope: Install new sewer lift station and sewer force main.
Schedule:Construction should begin in September, 2012 with a forecasted completion in early spring 2013.
Traffic Control / Street Closures: Mostly partial residential road way closures.
Cost: $1.4 million dollars
Funding Source: Sewer Service Fund
Central Park Irrigation Reservoir Modifications- CC-1382
Project Location: Central Park adjacent to Park Bench Cafe
Project Need: Existing irrigation pump station is no longer in use. New pump facility is already installed and in operation.
Project Scope: Remove unused and obsolete irrigation pump system and intake reservoir and add landscaping.
Schedule: Work started on August 13, 2012 and is to be completed by early November.
Traffic Control / Street Closures: None
Cost: $100,000.00
Funding Source: Water Fund
Sunset Beach Water Main Project - CC 1412
Project Location: Various locations in Sunset Beach
Project Need: Existing water mains are undersized and have poor circulation.
Project Scope: Install new water mains, services, and fire hydrants in selected locations to improve water quality, water pressure and fire protection. All affected alleys will be resurfaced after pipeline work is complete.
Schedule: Work should start in September.
Traffic Control / Street Closures: Daytime closure of alleys during pipe work. Some alleys will be closed for extended periods during roadwork.
Cost: $1.3 M
Funding Source: Water Fund
FY 2011/12 Sewer Rehabilitation Project - CC 1419
Project Location: Various locations
Project Need: TV inspection has found that the sewer mains on this project have degraded to the point that they need replacement or lining.
Project Scope: Install liner in degraded sewer mains using trenchless method.
Schedule: Work should start in late August.
Traffic Control / Street Closures: Minor daytime closures during work.
Cost: $88,000
Funding Source: Sewer Service Fund
FY 2011/12 ADA Curb Ramp Project - CC 1434
Project Location: Various locations
Project Need: Provide for wheelchair accessible corner ramps in various residential streets.
Project Scope: Remove existing sidewalk and curb and construct wheelchair accessible corner ramps.
Schedule: Work should start in mid September 2012.
Traffic Control / Street Closures: No parking adjacent to construction during working hours
Cost: $63,000
Funding Source: Community Development Block Grant Funds (HUD)
Tree Petition (Aulnay Lane) Project - CC 1418
Project Location: Aulnay Lane
Project Need: Aulnay Lane is on the list established by the Tree Petition Program and was picked for reconstruction based on longevity on the original chronological list and on the subsequent list based on current street condition.
Project Scope:Reconstruction includes tree removals and replacement, sidewalk, curb and gutter repair and replacement as necessary. Pavement overlay or a slurry seal will be applied to the street surface.
Schedule:Work anticipated starting in September 2012 and is expected to up to 3 months.
Cost: $478,000
Funding Source: Gas Tax
Waterline Extension Project - CC 1388, 1430, 1431
Project Location: Various locations in Huntington Beach
Project Need: To improve the looped fire protection in the area along Attleboro Circle, the homeowner association for Tract 5581 and Elm Lane as well as eliminate water quality concerns.
Project Scope: Install new waterlines in the distribution system in selected locations to improve fire protection, water quality and water pressure.
Schedule: Work is scheduled to start in September 2012 and take 2 months to complete.
Traffic Control / Street Closures: Daytime lane closure on Warner Avenue during pipe work.
Cost: $139,000
Funding Source: Water and Water Master Funds


