Infrastructure Construction in Progress

UpdatedFebruary 2014

Algonquin Sewer Lift Station and Force Main Replacement Project - CC-1415
Project Location: On Algonquin between Pearce and Boardwalk
Project Need: Replace antiquated sewer lift station and force main.
Project Scope: Install new sewer lift station and sewer force main.
Schedule: Construction began in September, 2012 and work is anticipated to be completed in late March 2014.
Traffic Control / Street Closures: Mostly partial residential road way closures.
Cost: $1.4 million dollars
Funding Source: Sewer Service Fund


Sunset Beach Water Main and Pavement Replacement Project, CC1429
Project Location: 9 Streets and Alleys in the Sunset Beach.
Project Need: the City identified old, existing water mains located within eight (8) alleys in the Sunset Beach area,

Project Scope: the City identified approximately 1,200 lineal feet of old, existing water mains located within eight (8) alleys in the Sunset Beach area. This project will replace the existing 3-inch to 4-inch asbestos cement pipelines installed in the 1950s with 6-inch diameter PVC pipelines.
Schedule: Forecast start – January 2014 – 170 working day duration
Cost: $1,650,000
Funding Source Water and Gas Tax Funds


__________________________________________________

Brookhurst/Indianapolis Emergency Sewer Line Repairs, CC1487
Project Location: With the Intersection of Brookhurst and Indianapolis.
Project Need: To repair a damaged sewer line and repair the intersection

Project Scope: Repair the damaged sewer and reconstruct the roadway
Schedule: Begin repair work 2/24/14 – 40 working days
Traffic Control / Street Closures: One lane of traffic in each direction on Brookhurst Street. No left turns to northbound Brookhurst from Indianapolis There will be times when the entire intersection will be closed to all traffic and a detour will be in place.
Cost: $900,000
Funding Source Sewer Funds


__________________________________________________

Beach Boulevard Sewer Line Project, CC1443
Project Location: Beach Boulevard between Ellis Avenue and Slater Avenue along with a portion of Ellis Avenue from Beach to one block east
Project Need: To increase sewer capacity to accommodate future developments along Beach Boulevard

Project Scope: Install 5,400 feet of 8� sewer Line in Beach Boulevard and 350 feet of 12� sewer line in Ellis Avenue
Schedule: Begin work 3/10/14 – 110 working days
Traffic Control / Street Closures: Lane Closure on Beach Boulevard and a portion of Ellis Avenue during Construction. Most work will occur during the hours of 10 Pm and 7 am with occasional work on Ellis during the daytime normal working hours
Cost: $2,000,000
Funding Source Sewer Funds


__________________________________________________

Project Name: CC-1370 Warner Avenue Gravity Sewer / Pump Station ‘C’ Project

Location: Warner Avenue, between Brightwater Drive and Pacific Coast Highway AND Pacific Coast Highway between Warner Avenue and Coral Cay.

Project Need: Four existing pump stations will be taken out of service and the sewage will be gravity fed to the new pump station located near the intersection of Brightwater Drive and Warner Avenue. The new line will also increase the capacity for the residents and businesses in the area.

Contractor Name: Artukovich & Sons

Scope: Construct 4,000 feet of new gravity sewer main along Warner Avenue and Pacific Coast Highway. The gravity line will be installed using the “open trench� method in which 10 separate traffic control phases will be utilized for the installed to minimize traffic impacts. The new gravity line will allow for the abandonment of 4 existing, problematic pump stations. The new underground pump station ‘C’ will be constructed in the Huntington Beach Yacht Club parking lot. The landscaping for the project will be performed by the Bolsa Chica Conservancy who is uniquely qualified to provide native plant restoration within the City right of way adjacent to the Conservancy lands. The Conservancy has access to native seed stock, and experience salvaging and reestablishing native plants in disturbed areas.

Traffic Control / Street Closures: Mostly lane closures along Warner Avenue and Pacific Coast Highway.
Start Date: November 2013 Estimated Completion Date: Fall 2014
Cost: $11 million Funding Source: Local sewer funds

For current phase of the work in progress go to: http://www.huntingtonbeachca.gov/WAGS

 

 

 

home | residents | visitors | business | government | services | site map | terms of use/privacy statement | contact us | directions to city hall |

2000 Main Street, Huntington Beach, California 92648
© Copyright 2002-14 City of Huntington Beach. All rights reserved.
Surf City USA is a registered trademark of the Huntington Beach Marketing and Visitors Bureau.